ReNew Power looks to exit Tamil Nadu wind-based power projectIllustrative image – not actual.
ReNew Power is looking to exit an agreement to build 265 MW wind power project in Tamil Nadu, citing ‘force majeure events’.

The company has petitioned the Central Electricity Regulatory Commission (CERC) to terminate the power purchase agreement (PPA) it signed with the government of India-owned Solar Energy Corporation of India (SECI) in September 2018.

ReNew Power won the project in SECI’s fourth round of wind capacity auctions on April 2018, quoting a tariff of Rs 2.52 a kWhr.

In its petition, ReNew cited it is unable to implement the project because of delay in allocation of land and commissioning of the transmission system to evacuate power. It has further cited delay in adoption of tariff by SECI and COVID-19 as reasons.

ReNew Power has taken a stand that if a force majeure event continued for more than nine months, it is entitled to terminate PPA. It has requested the Central Electricity Regulatory Commission (CERC) to tell SECI to return the bank guarantee.