Reliance Power has agreed to return approximately 956 acre of land acquired for the 7,480 MW Dadri power plant, to the Uttar Pradesh government.
The proposed land has been involved in legal issues with the Allahabad High Court verdict since December 2009. The High Court judgement had made it mandatory for the UP government to get a no-objection certificate (NOC) from each seller or get the sellers to return the compensation received, to the government. Reliance Power and the state government had both contested the high court ruling.
Finally, Reliance Power submitted an affidavit to the Supreme Court a fortnight ago, stating that it would have set up the power project had there been no legal issues with the land acquired. The company also claimed that in the 10 years since the project was envisaged, it has become more difficult to get a regular supply of natural gas. The power project was likely to be implemented with an investment of Rs 25,000 crore.