Reliance Power quits Tilaiya UMPPIllustrative image – not actual.
Reliance Power has announced that it has terminated the contract for the Rs 36,000 crore Tilaiya ultra mega power project in Jharkhand, over inordinate delay in land acquisition.

 

The company was awarded the 3,960 MW UMPP in February 2009, based on the tariff-based bidding managed by Power Finance Corporation (PFC).

 

The required land is yet unavailable for the company. Even the forest land in the power station area -- for which Stage-II forest clearance was accorded by the Central government in November 2010 -- has not been handed over till now.

 

As far as the coal block allotted for the project is concerned, the land acquisition process is yet to be initiated, for which the application was submited in Februaury 2009.

 

According to the company, based on the current estimates of the land handover process, the project cannot be completed before 2023-24.

 