Reliance might face penalty over gas supply delaysIllustrative image – not actual.

The Union petroleum ministry might penalize Reliance Industries for delays in supplying gas to NTPC's Kawas and Gandhar gas-fired power projects in Gujarat.

Reliance has been dithering on gas supplies, shifting supply schedule from end-2007 to mid-2008 now. NTPC is in the midst of adding 2,600 MW of power capacity at its Kawas and Gandhar plants in Gujarat for which it would need around 13 mmscmd of gas.

Reliance has still not entered into a final gas supply agreement with NTPC despite winning the order for gas supplies almost two years ago.

The issue acquired a new turn in September 2005 when Reliance imposed fresh conditions on the gas supply agreement seeking alterations in the pricing structure and some concessions in compensation of non-supply.

In October 2005, NTPC decided to negotiate with Gail (India) as a prospective supplier to the Kawas and Gandhar projects. Gail has already committed to supply gas to NTPC's Kayamkulam project in Kerala where capacity is being raised to 2,600 MW from the existing 350 MW.