Illustrative image – not actual.The Reliance Infrastructure has bagged an engineering, procurement and construction (EPC) contract worth Rs 3,647 crore from the Tamil Nadu Generation and Distribution Corporation (TANGEDCO).
The contract is for balance of plant (BoP) package and allied civil works for 2x800 MW supercritical coal-based Uppur Thermal Power project at Ramanathapuram district in Tamil Nadu.
The scope of work envisages design, engineering, supply, erection, testing and commissioning of BoP package and allied civil works on EPC basis. The project will be executed in 36 months.