Reliance Industries has filed a multi-million dollar plan with the government to develop the gigantic D-6 field offshore Andhra Pradesh, with production targeted to commence in August 2006.

Reliance plans to invest $500 million (Rs.2,250 crore) in Phase I to produce 500 million cubic feet per day (14 mmscd) of gas from August 2006.

Almost the entire output of Phase I would go towards supplying gas to NTPC's Kawas and Gandhar, for which the company plans to lay a 1,400 km pipeline from Kakinada to Uran, with a hook-up to Kawas and Gandhar.

The company would invest a further $800 million in Phase II to boost output to 40 mmscmd by 2008-09. This enhanced output would be used to feed the company's 3,740 MW Dadri power project in Uttar Pradesh.

Output would be further raised to 60 mmscmd if Reliance wins the supply order for NTPC's power plants in Kerala.