Reliance Energy has applied to the government for a coal linkage of 30 million tonnes for its thermal power projects of 12,000 MW at Hirma in Orissa and 1,000 MW at Akaltara in Chhattisgarh.

REL has sought 30-year coal linkages of 6 million tpa for the Akaltara project and 24 million tpa for the Hirma project. Both the projects will be taken up during the XI Five Year Plan period (2007-12). Phase I of the Hirma power project will involve capacity of 4,000 MW.

The earlier proposal to develop the Hirma power project was submitted to the State government in the mid-1990s. Reliance had then tied up with Hong Kong-based Consolidated Electric Power Asia Ltd (CEPA) to set up a 3,940 MW power project at the Hirma site. The project did not move forward owing to delays in the finalisation of PPAswith different states. Later, CEPA withdrew from the project, further hindering its progress. In the new proposal, the company has scaled up the proposed capacity three fold to 12,000 MW.

Reliance Energy is present in Orissa through its three electricity distribution firms - Nesco, Wesco and South - following its acquisition of BSES. Reliance Energy's entry into power generation in the state will bring synergy to its operations in Orissa.

In addition to these two projects, REL has also informed the coal ministry of conducting detailed feasibility studies of some prospective sites in Maharashtra, Uttar Pradesh, Madhya Pradesh and Jharkhand for its future projects.