Reliance commissions Unit-V of Sasan UMPPIllustrative image – not actual.

Reliance Power today announced that it had commissioned Unit-V of the Sasan ultra mega power project.


Unit-IV of the 3,960 MW (6 x 660 MW) Sasan UMPP was commissioned in May 2014. The company had achieved boiler light-up for Unit-V in July 2014.


With the completion of Unit-V, the power project has reached a capacity of 3,300 MW.


Madhya Pradesh gets 1,000 MW power from Sasan which will be increased to 1,500 MW on project completion. The state is getting power from the Sasan UMPP at the rate of 70 paise per unit.


By commisioning this unit, Reliance Power's total generation capacity has increased to 5,185 MW which includes 5,100 MW of thermal capacity and 85 MW of renewable energy-based capacity.

 