Illustrative image – not actual.The redevelopment work has commenced at Habibganj station in Bhopal, Madhya Pradesh on 7 May 2020 after a gap of nearly two months. The work was nearing completion when the lockdown was announced on 25 March 2020.
Now, only seven percent work is left, but the absence of labour remains a major hurdle. Currently, the work has commenced with only 50-55 labourers. Escalators that were supposed to reach Bhopal from China in the first week of January 2020 are yet to come. Habibganj is the first railway station in the country to be redeveloped through public-private partnership (PPP) mode under the station redevelopment programme of the Indian Railways.
The Indian Railway Stations Development Corporation (IRSDC), a joint venture (JV) of IRCON and the Rail Land Development Authority (RLDA), is the nodal agency for undertaking development works at railway stations under the Ministry of Railways.
The revenue realised from real estate development and commercial facilities at the station is being utilised for redevelopment and maintenance of the station. Revamp of Habibganj station into a world-class station was launched in July 2016 at an estimated cost of Rs 450 crore.
However, the work started only in January 2017 with a deadline to complete it in three years. The project is divided into two parts -- Rs 100 crore was earmarked for facelift of the station while the remaining Rs 350 crore was for commercial facilities.
While the deadline for the facelift was set as 31 March 2020, the deadline for construction of commercial facilities is 2022.