Reconstruction work begins for Patripool ROB in KalyanIllustrative image – not actual.

The reconstruction work has commenced on Patripool rail-over-bridge (ROB) in Kalyan, which was dismantled in August 2018.

The Maharashtra State Road Development Corporation (MSRDC) has altered the basic design of the structure, which will now have six lanes to prevent traffic from being held up.

The new bridge is likely to be opened to the public by February 2020.

Two mega blocks of five hours each are likely to be operated on the Central Line in December 2019 to carry out construction activities of the bridge.

As per the earlier plan, four-lane bridge was proposed to be constructed. However, the road below the bridge has six lanes.

In order to prevent the flow of traffic from being restricted from either end of the bridge, it was decided to add two more lanes and the amount sanctioned for the project has increased from Rs 31 crore to Rs 34 crore.

The nodal agency has received a nod from the Maharashtra state government for the project.

The 104 year old Patripool bridge, which connects Kalyan to Dombivli, Ulhasnagar, Ambernath, Badlapur, Thane, Bhiwandi and Navi Mumbai, was dismantled by the Central Railways in November 2018.

 