Illustrative image – not actual.Rural Electrification Corporation (REC) is likely to finalise funding arrangement for three power generation projects of 2,200 MW estimated to cost nearly Rs.10,725 crore by mid-October 2008.
REC is likely to sign the proposed week loan agreements with the Tamil Nadu Electricity Board (TNEB) and the NLC Tamil Nadu Power Limited (NTPL), a SPV floated by the Neyveli Lignite Corporation (NLC) and the TNEB.
Of the total cost of the projects, REC has sanctioned Rs.8,087 crore. All the projects are coal-fired. While two units of 600 MW each are to come up in the premises of the TNEB’s North Chennai Thermal Power Station (NCTPS) at Athipattu in Chennai, two units of 500 MW will be established at Tuticorin, the location of the NTPL project. For funding purposes, the two additional units at the NCTPS are regarded as two projects.