Illustrative image – not actual.GMR has decided to put on hold the controversial real estate project from the development of the Delhi international airport.
However, the real estate project is stalled as DIAL insisted the deposits collected from real estate developers were not part of the top line revenues that were supposed to be shared with the Aiports Authority of India (AAI). The deposits were being used as equity to finance the project.
DIAL had earlier cleared a plan under which refundable deposits of around Rs.2,750 crore raised from developers of the real estate project (which includes hotels and commercial space) will be used to part-fund the Rs.8,950 crore airport modernisation.
It has now mooted an alternative plan, which has been accepted in-principle by the civil aviation ministry, under which the amount of Rs.2,750 crore will be raised through equity from stakeholders in proportion to their participation in the project.
Under the new scheme, GMR which holds 50.1 per cent in DIAL will have to pump in around Rs.1,386 crore (in addition to Rs.593 crore as per the previous model), AAI which has a 26 per cent stake will have to shell out around Rs.719 crore (in addition to around Rs.308 crore committed earlier) and other partners will have to put in Rs.645 crore (in addition to Rs.299 crore).
The total equity infusion from all the shareholders will now amount to around Rs.4,000 crore, up from Rs.1,200 crore as per the earlier model.
Originally, of the total project worth of Rs.8,950 crore, only Rs.1,200 crore was supposed to come as equity, Rs.50 crore through internal accruals, Rs.4,950 crore from bank loans, and Rs.2,750 crore for real estate projects was to come as refundable deposits.