Illustrative image – not actual.Rashtriya Chemicals & Fertilisers is investing Rs.4,000 crore to increase the manufacturing capacity of urea and ammonium at its Thal unit in Raigad district of Maharashtra.
Of the total investment, around Rs.450 crore will be invested to de-bottleneck its old urea plant, which will increase the plant's capacity from 18.5 million tpa to 20.3 million tpa while Rs.3,500 crore will be invested for the brownfield expansion of its manufacturing facilities, which will increase the capacity by another 10 million tpa.
Work on the de-bottelnecking project will start by April 2008 and is scheduled for completion within 18 months.
It is learnt that the ammonium-urea chemical complex expansion project at Thal has received the first stage clearance from the Department of Fertilisers and the Public Investment Board (PIB). The project is scheduled for completion by March 2010.
Also See:
GAIL, RCF signs MoU for coal gasification project (28-Dec-07)