Illustrative image – not actual.
The scope of work is setting up a 20 MW plant at Morbe dam in the adjoining Raigad district. This would be the first-ever solar project built on a dam.
The solar power solutions provider is expected to complete the set up by 31 March, 2015.
This contract was earlier awarded to Nirmal Datacomm on 26 February, 2014. However, it was terminated subsequently on 5 March, 2013 as the contractor did not deposit 3 per cent of the contract value as security within 10 days of award of contract.
Ray Power Experts recently commissioned its 20 MW solar project at Bikaner in Rajasthan on 16 October, 2014. Further, the company plans to expand its business portfolio, It envisions to enter into new verticals such as independent solar power parks, solar roof top models and among others.
More Project Info:
Solar Photovoltaic Power (Morbe Dam) Project