RattanIndia Power commissions fourth 270 MW Unit in MaharashtraIllustrative image – not actual.
RattanIndia Power made an announcement on 9 March 2015, that it had commissioned the fourth 270 MW unit of the 1,350 MW Phase-I of its thermal plant at Amravati, in Maharashtra.

 

The company, earlier known as Indiabulls Power, is setting up a 2,700 coal-based plant in Amravati, in two phases of 1,350 MW each. This is the first phase and it involves five units of 270 MW each. The estimated cost of Phase-I is Rs 7,493.33 crore.

 

With the commissioning of the fourth unit, the total capacity of the first phase has increased to 1,080 MW. By the month-end, the fifth unit of 270 MW is expected to be commissioned and it will take the total installed capacity to 1,350 MW.

 

For this 2,700 coal-based plant in Amravati, RattanIndia has assured coal linkages from public sector Coal India, and has also signed fuel supply agreements with South Coalfields, a subsidiary of CIL. It has also signed a long term PPA for 1,200 MW with Maharashtra State Electricity Distribution Company (Mahavitaran).

 

More Project Info:
Amravati Coal Based Power (Nandgaonpet) Project - Stage I

← All latest storiesBack to top →