Illustrative image – not actual.The gas will start flowing from the Dahej-Uran and Panvel-Dabhol pipeline at the project site from 12 July 2007 and will enable RGPPL to generate 1,400 MW and later supply it to the Maharashtra State Electricity Distribution Company (MahaVitaran).
Petronet LNG has already entered into an agreement up to September 2009 for the supply of 1.2 million tpa for the project and it has already succeeded in tapping 0.6 million tpa needed to generate 700 MW from the third unit.
Commercial production from the Dabhol plant was earlier planned to begin from December 2006. However, due to the non-availability of gas and resolution of various other issues, it has been re-scheduled to November-December 2007.
The board of NTPC has approved an advance of Rs.500 crore to Ratnagiri Gas and Power (RGPPL), the first tranche of which will be released immediately.
Earlier, GAIL India, which holds 28.33 per cent equity in RGPPL, had offered to pump in Rs.500 crore for takeover of the LNG facility. However, GAIL argued that prima-facie it did not see the standalone LNG project as viable. Subsequently, GAIL withdrew its proposal and NTPC later offered to make available funds up to Rs.500 crore with a 'first right of refusal' if and when it is decided to hive-off the LNG facilities.