Ratnagiri gas & power to get Rs.550cr state aidIllustrative image – not actual.

The Maharashtra government will lend Rs.550 crore to Ratnagiri Gas & Power as a bridge loan to ensure that its plant starts running to full capacity of 2150 Mw by the end of November 2007.

The decision to this effect was taken at the meeting between the officials of NTPC and GAIL and the representatives of the state government led by state energy minister Dileep Walse-Patil on 14 February 2007.

The government has agreed to give Rs.45 crore immediately to RGPPL to ensure turbine of 330 Mw unit of block II of Dabhol is carried out by the end of March and block II starts generating power at its full capacity of 740 Mw. The remaining amount will be raised by the government from financial institutes and given to RGPPL to ensure repair and maintenance work of other two block that is to be completed by November 2007. The plant lay idle after Enron, the promoter of Dabhol, went bust in 2001 and the plant machinery got extensively damaged.

Already Rs.10,000 crore have been pumped by NTPC, GAIL and various financial institutions to revive the project and they are no longer willing to lend further to the project. Moreover, financial institutes won't lend money to the project unless power purchase agreement (PPA) and contract for gas is in place. But early revival of the project is the requirement of the state considering the power shortage.

Earlier, the state cabinet cleared proposal to give around Rs.1300 crore to the state-owned power utility MSEDCL to buy expensive power during summer months.