Illustrative image – not actual.In February 2017 the company was accorded terms of references (ToR) for the expansion project. The environmental clearance (EC) was accorded to the project a year later in 2018.
In November 2017 KBR bagged an order to provide a technology license and basic engineering design for the project.
As per the latest update available with Projects Today, Rashtriya Chemicals & Fertilizers has begun discussions with various vendors for sourcing equipment. Also, KBR has commenced initial work for finalising specifications required for revamping the ammonia facility. Work on the project was expected to commence by May 2019.