Illustrative image – not actual.Nuclear Power Corporation of India Ltd (NPCIL) is unlikely to commission its 220 Megawatt electric (MWe) Unit V of Rajasthan Atomic Power Project (RAPP), located at Rawatbhatta, near Kota in Rajasthan by 31 August 2009, the cut-off date for the first 100 days of the Union Government.
NPCIL has reportedly revealed it to the Union Ministry of Power that the unit is yet to be supplied with fuel and will be commissioned only by end-December 2009.
NPCIL is currently operating 17 nuclear power units, at six locations in India, and is implementing five more at three locations. The company intends to add 2,660 MWe in the XIth Plan period, consequent to the completion of its ongoing projects.
Currently, India has an installed nuclear generation capacity of 4,000 MWe, which is expected to increase to 20,000 MWe by 2020, and, further, to 63,000 MWe by 2032.