Rana Sugars will commission two new sugar units in Uttar Pradesh, with a combined capacity of 10,000 tccpd. Each unit of 5,000 tccpd will have a 20 MW bagasse-based cogeneration power plant.

Discussing the detailed progress, senior officials told ProjectsToday that the civil works pertaining to the first unit, coming up at Beluara in Muradabad district, has been completed. The mechanical package will be executed soon with full commercial operations expected by November 2006. KS Projects & Process Engineers Pvt Ltd is rendering consultancy for the civil and mechanical work. The cost of the sugar plant along with the 20 MW cogeneration plant is an estimated Rs.210 crore.

An identical project is coming up at Shahbad in Rampur district. This 5,000 tccpd along with a 20 MW cogeneration plant is targeted for completion by December 2006. Around 90 per cent of the civil work currently stand complete, according to Rana Sugars officials.

Meanwhile, a Rs.60 crore project is underway at its existing sugar unit at Village Buttar Seviya (Baba Bakala tehsil, Amristar district) where capacity of the cogeneration plant is being expanded 20 MW to 54 MW. This expansion is scheduled for completion by end-October 2006.

In another development, Rana Sugar commissioned in March 2006 a new 60 klpd distillery at Lounka in Amristar district in Punjab. The Rs.35 crore project was under physical implementation since April 2005.