Illustrative image – not actual.A 50:50 JV between Ramky Infrastructure and IL&FS Transportation Networks has tied up funds with respect to the debt syndication of Rs 1,060 crore through Canara Bank.
The consortium had bagged a project from the Andhra Pradesh Road Development Corporation for four-laning (212.5 km) of the existing two-lane stretch from Narketpally to Addanki and Medarametla road on state highway-II. The cost of the project is Rs 1,760.53 crore.
The concession agreement for the project, to be executed under DBFOT format, was signed on 23 July 2010. The project has a concession period of 24 years, including the construction period of 910 days.
Related Links:
Project profile