Ramco Cements ongoing capex programme delayed due to COVID-19Illustrative image – not actual.
Ramco Cements ongoing capital expenditure (capex) programme has been delayed due to COVID-19. 
 
The railway siding in Kolaghat, West Bengal, is expected to be operational in September 2020, while the grinding plant of one million tpa along with railway siding in Odisha is expected to be commissioned before September 2020. 
 
The company has undertaken waste heat recovery systems (WHRS) project in Jayanthipuram, Andhra Pradesh. Out of 27 MW of the proposed WHRS, units of nine MW each are expected to be commissioned on or before September and December 2020 respectively. 
 
The company aims to complete the clinkering unit of 1.5 million tpa along with nine MW WHRS in Jayanthipuram and 2.25 million tpa clinkering unit in Kurnool before March 2021, albeit difficulties experienced during the pandemic time. 
 
The one million cement grinding facility with 18 MW thermal power plant (TPP), 12 MW WHRS and railway siding in Kurnool are expected to be commissioned in FY2021-22. 
 
The construction activities in all the project sites have started picking up. The company has incurred Rs 257 crore during Q1/FY21 towards total capex including for the above-mentioned ongoing capacity expansion programme. 
 
The balance capex to be incurred as on 30 June 2020 is Rs 1,180 crore for its ongoing capacity expansion.