Illustrative image – not actual.The greenfield Ramayapatnam Port along the Nellore coastline is advancing rapidly and is targeting an operational launch by December 2026.
Phase-A of the port has achieved 80.50 percent physical progress and 73.95 percent financial progress against its sanctioned project cost of Rs 4,929.39 crore. The accelerated execution follows a high-level infrastructure review in May, where Andhra Pradesh Chief Minister N Chandrababu Naidu directed time-bound completion of major port and infrastructure projects. Key components are nearing completion, with outer breakwaters at 97.98 percent and berth construction above 90 percent. Supporting connectivity infrastructure is also progressing to facilitate freight movement and minimise logistical bottlenecks.
Meanwhile, the 7.4-km railway link connecting the port to Tettu station has reached 30 percent completion and is planned for completion alongside the port.