Ramanathapuram water supply scheme to complete by April 2009Illustrative image – not actual.

Tamilnadu Water Supply & Drainage Board's Ramanathapuram combined drinking water supply scheme will be completed by April 2009, ahead of its scheduled date of completion in March 2010. The project is being implemented at a cost of Rs.616 crore

Currently, around sixty-two per cent of the works has already been completed and the project is progressing at a much rapid pace. The scheme will provide drinking water to five municipalities, 11 town panchayats and 3,163 rural habitations in Pudukottai, Sivagangai and Ramanathapuram districts. Four collector wells were being established on the Cauvery River bed at Kadiyakurichi and Mutharasanallur and the scheme will pump about 100 million ltrs a day. Pumping mains will be laid for a distance of 749.21 km up to Ramanathapuram/Rameswaram. The project has been split into seven packages.

Seventy-five per cent of the works on the construction of the first collector well, 50 per cent on second, 20 on the third and 30 per cent on fourth collector wall have been completed so far. Pumping/gravitational mains have been laid for about 412 out of the 739 km and distribution mains have been laid for about 68 km out of the 469 km.

← All latest storiesBack to top →