Ramagundam power project awaits signing of tri-partite MoUIllustrative image – not actual.

The BPL Power-promoted 520 MW Ramagundam power project in Andhra Pradesh, would achieve financial closure once a tri-partite MoU between the Government of Andhra Pradesh, Transmission Corporation of Andhra Pradesh (APTransco) and the project lenders, is signed.

 

This MoU would be part of a new reform based approach to project financing. Under this new approach, the State government and APTransco will try to achieve reforms in the power sector within a time frame and the lenders will finance the project based on the reform milestones achieved. Reportedly, according to the MoU, the lenders would also have a concurrent charge on the revenue of APTransco along with the working capital bank.

 

The power project is estimated to cost Rs.2,776 crore and would have a debt equity ratio of 70:30. The project has already received environmental clearance and CEA techno-economic clearance. The PPA for the project has also been signed.