Rajiv Gandhi Thermal project to commence generation in JulyIllustrative image – not actual.

The Haryana Power Generation Corporation Ltd (HPGCL) is likely to commission the 600 MW Unit-I of the 1,200 MW Rajiv Gandhi Thermal Power Project at Khedar in Hisar district of the state by end-July 2009.

HPGCL has completed 76.01 per cent of the work on the plant. In project engineering and procurement a progress of 86.7 per cent and 83.6 per cent, respectively, has been achieved.

Besides, the project has completed the hydraulic test of the boiler of Unit-I on 1 March 2009 and the Unit-II hydraulic test was successfully completed on 18 April 2009.