Illustrative image – not actual.The Rajasthan Rajya Vidyut Utpadan Nigam (RRVUNL) has cancelled tenders that were bagged by BHEL for two separate thermal power projects in the state.
The RRVUNL has scrapped EPC tenders worth Rs 12,000 crore for two 660 MW units — each for Suratgarh and Chhabra, respectively, without specifying any particular reasons.
Even though the tenders were finalised in January 2011, the RRUVNL initiated price negotiations with BHEL only in January 2012. When the tenders were floated in November 2009 and opened in April 2010, there were three bidders — BHEL, BGR and Russia’s Power Machines. The tenders were for design, engineering, manufacture, assembly, testing at works, supply, civil structural and architectural works, erection, testing and commissioning of main plant and balance of plant on EPC basis.