Railways to cover last mile of electrification in second half of CYIllustrative image – not actual.

The Indian Railways is likely to complete the total electrification project of its broad gauge network only in the second half of the calendar year. Around 95 percent of the network had been electrified by the end of March. This will be in time to implement the 100-day agenda of the new government.

Originally, full electrification was scheduled for December 2023, however, the deadline was extended to the end of 2023-24. It has now been pushed further due to ongoing work. In seven states and territories, electrification is minimal or yet to commence. Significant work remains in North Eastern states and others like Goa, Karnataka, Kerala, Rajasthan, and West Bengal.

The FY24 budget allocated Rs 8,070 crore for electrification, with nearly half now expected to be spent in FY25.  Indian Railways aims to achieve the world's largest green railway network, and will contribute to India’s target of achieving net-zero greenhouse gas (GHG) emissions by 2070.

The pace of electrification accelerated from FY18, marking a notable increase to over 6,000 route km annually until FY22. Railways achieved 6,500 route km in FY23 and set a target of 6,500 km for FY24. However, it was only half met with just around 3,500 route km achieved in FY24. This leaves a similar route km of work to be completed over the next few months. 

Electrification varies across states, 14 are fully electrified, while nine are at above 90 percent, and two at above 80 percent. 