Illustrative image – not actual.On 14 June 2007, Indian Railways signed a long-term coal transportation agreement with Nagarjuna Power Corporation for a term of 25 years.
Under the agreement, Nagarjuna Power assures Railways of about 2.8 million tpa of coal traffic each year. In return, Railways assures the company to make available wagons to move coal (a maximum of 89 rakes per month). The coal, which will be imported, will have to be moved 36 km from New Mangalore Port to a siding near the 1,015 MW thermal power plant near Padubidri (located near Konkan Railway tracks).
For transporting the coal by trains, Nagarjuna Power will have to pay freight charges that will be five per cent higher than what Railways levies for coal at any given time. The company will have to pay freight charges for the assured load even if it fails to load or unload the assured quantity as per the provisions.