Indian Railways has revised its methodologies for award of projects to expedite the execution of projects in the country.
According to the new policy the tendering process and award of projects, which used to take two years or more, would be completed in six to nine months. The new policy would also allow each railway zone to call tenders immediately after a request for in-principle approval (IPA) is received by the NITI Aayog without waiting for its approval. However, a financial commitment to the awardees can be made only after all requisite approvals are in place.
Under the new policy, the final location survey will be done immediately after inclusion of the work in railway budget, after which the zonal railways will send detailed project report (DPR) to the Railway Board.