Illustrative image – not actual.The Union Ministry of Railways has reportedly put the greenfield rail infrastructure projects on hold.
The electric locomotive unit in Madhepura and a diesel locomotive unit in Marhoura in Bihar are among the projects that have been pushed on the backburner. Even though a Cabinet note to revive the projects on PPP basis has been sent to the concerned ministries, there has been no follow up on these projects.
The Rs 1,300 crore Madhepura electric locomotive project was announced in the Railway Budget of 2007. The project envisaged developing the greenfield unit on PPP basis for procurement of 8,000 locomotives over eight years.
However, in early 2009, the ministry had decided to fund the project through railway coffers and make it a government project. The Cabinet approved the proposal of setting up the factory as a Railways production unit in February 2009.
However, the Planning Commission advised it not to take it up as government-funded project. Almost similar is the case of the diesel locomotive unit at Marhoura.