The Railways and National Thermal Power Corporation (NTPC) signed a memorandum of understanding (MoU) on 18 February 2002, to set up captive power plants with a total capacity of 2,000 MW, for the Railways.

 

The 50:50 joint venture would invest about Rs.9,000 crore over the next five years to set up 300-500 MW units near the traction load centres of the Railways. According to the Railway board chairman, Mr R N Malhotra, 6-7 traction sites have been identified for setting up the power plants. A final decision on the location and capacity of the plants would be taken in a month's time by a committee, which would prepare a project report on the same.

 

NTPC chairman, Mr C P Jain, stated that a special purpose vehicle would be set up for executing the joint venture power projects, which could be an expansion of the existing plants or greenfield capacity addition at the traction load centres. He further said that the power plants would be coal-based as of now, but possibility of gas-based power plants could not be ruled out.

 

The total cost of the project has been estimated at Rs.11,000 crore, of which Rs.2,000 crore will be for the wheeling charges. The debt-equity ratio of the project would be 70:30, with the Railways and NTPC contributing Rs.1,650 crore each.

 

The Railways’ foray into power generation is expected to help it save between Rs.1,000-1,500 crore annually on electricity bills, according to the railway minister, Mr Nitish Kumar. The Railways have rationalised the project on the ground that they spend Rs.4,500 crore annually on electricity for traction and non-traction purposes. It purchases majority of the power from state electricity boards, which charge 2-3 times the rate at which they could purchase power from central generating agencies. The average cost of procurement of power from the SEBs works out at Rs.4.28 per unit for about 10,000 million units of power consumption, while the joint generation of power would help the Railways save 40 per cent of the energy bill.

 

Of the Rs.32,000 crore annual expenditure, the Railways spent close to Rs.8,000 crore on fuel needs, of which, 63 per cent was for traction electrification. The Railways have identified various schemes for availing of direct power supply from NTPC, Nuclear Power Corporation and Neyveli Lignite Corporation in different parts of the country.