Illustrative image – not actual.The Indian Railways would need a grant of Rs.13,032 crore to expedite 42 identified projects, most of which would be completed by 2003. These identified projects include laying of new lines, gauge conversions, doubling and electrification projects.
Of the total amount of grant sought, Rs.7,033.77
crore would be required for laying 12 new lines, including the national
Jammu-Tawi-Udhampur project, Jammu & Kashmir. This project is likely to get
Rs.3,244 crore of the total grant amount, while the new line project on the Hubli-Ankola
route would get Rs.1,000 crore for the movement of iron ore traffic for export.
A sum of Rs.3,272.30 crore has also been sought for nine
gauge conversion projects. Of this amount, Rs.609 crore has been sought for the
Kanpur-Kasganj-Mathura and Kasganj-Bareilly sectors in Uttar Pradesh, while another
Rs.441.63 crore for Surendarnagar-Pipavav port project, in Gujarat. All three projects
are expected to be completed by 2003.
Grant has also been sought for the Rs.325.98 crore Arisikere-Hassan-Mangalore
stretch, Karnataka and the Rs.535.88 crore New Jalpaiguri-Siliguri-New Bongaigaon
project. These two projects are expected to provide broad gauge hinterland
connectivity to the Mangalore port and provide a double line between New
Jalpaiguri, West Bengal and New Bongaigaon, Assam to deal with traffic to and
from the North-eastern region, respectively.
The identified projects include six electrification projects,
which need a sum of Rs.1,412.21 crore. Of this amount, Rs.363.36 crore has been
earmarked for the Sitarampur-Danapur-Mughalsarai sector, including the
Rampur-Dumra-Garhara-Barauni stretch under the Eastern Railway.
The Railways have also identified 15 doubling works,
for which Rs.1,313.92 crore grant has been sought. The doubling work of the Gooty-Renigunta
stretch would require Rs.304.5 crore.