Railways earmarks Rs.30,000 cr for infrastructure developmentIllustrative image – not actual.

Indian Railways (IR) is mulling over an investment of Rs.30,000 crore to upgrade its infrastructure.

The upgradation plan includes renewal of 2,941 km railway tracks that will require about 339,228 tonne of steel and renewal of sleeper sheets along 2,382 km of railway lines. IR is developing 300 railway stations into model stations for which the work is underway. It is also developing 23 world class stations, for which construction work on four has already started.

The Railways will also be setting up a 1,000 MW thermal power plant as part of a JV deal with NTPC at Nabi Nagar, Bihar at a total outlay of $1.19 billion (Rs.5,352 crore).

Besides, IR's electrification target for the Eleventh Plan has been enhanced to 3,500Kms. Similarly, the electrification target for the current year has been increased from 700km to 1,000 km next year. Electrification is likely to be undertaken over 1,200kms with Rs 1,000 crore, between Ghaziabad-Moradabad, Shoranur-Mangalore and Gondia-Ballarshah, among others.

Also See:

Indian Railways to consider $800 million ADB fund(01-Feb-08)