Railway projects dogged by land acquisitionIllustrative image – not actual.

The South Western Railway has not been able to complete as many as 12 major railway projects in Karnataka, owing to land acquisition delays.

There has been no progress in the process of acquisition of 1,129.75 ha in 15 districts which has been delaying the completion of the railway projects in the state. Around 42 applications for acquisition of land have been pending before Deputy Commissioners of 15 districts. The state government has directed the concerned Deputy Commissioners to expedite the process.

The delayed projects are: Tumkur-Rayadurg railway line (282.99 ha in Tumkur district), Bidar-Gulbarga (328.30 ha in Gulbarga), Bagalkot-Kudachi (272.09 ha in Bagalkot), Kottur-Harihar (2.43 ha in Davanagere), Bengaluru-Hassan (5.51 ha in Bengaluru), Ramanagaram-Mysore and Bengaluru -Hassan (68.50 ha in Ramanagaram), Chikmagalur-Kadur, Birur-Shivani and Arsikere-Birur (48.11 ha in Chikmagalur), Ramanagaram-Mysore and Bengaluru-Hassan (83.94 ha in Mandya district), Kambaghanvi-Dharwad (3.76 ha in Dharwad), Bengaluru-Hassan and Arsikere-Birur (10.65 ha in Hassan), Kolar-Chikkaballapur (8.70 ha in Kolar); Kolar-Chikkaballapur (2.98 ha in Chikkaballapur), Ramanagaram-Mysore (3.59 ha in Mysore), Raichur-Gadwal (0.4 ha in Raichur) and Gulbarga and Bidar (forest lands).

← All latest storiesBack to top →