Illustrative image – not actual.The Railways Ministry is reportedly considering a proposal to exclude the four major bridges from the Rail Vikas Yojana.
Rail Vikas Nigam Ltd (RVNL) – the executing agency for the Rs.15,000 crore project – has planned to implement the four major bridges totally costing Rs.3,500 crore on BOT basis or through the special purpose vehicle route. This is being done to obviate the difficulties associated with segregation of revenues once the bridges are commissioned. The Railways Ministry is reportedly approaching the World Bank to seek separate funding for these bridges projects in which work has already begun.
The Railways have already tied up $313.6 million (Rs.1,500 crore approx.) from the World Bank for the GQ projects. A team of World Bank officials is understood to be arriving in India on 3 October 2003 to discuss the additional funding issue. Of the total project cost of Rs.15,000 crore, India is seeking Rs.6,500 crore as World Bank assistance.
Backgrounder:
The Rail Vikas Yojana is a Rs.15,000 crore project
announced by the Prime Minister on 15 August 2002. This Rs.15,000 crore
project, being implemented by a special purpose vehicle Rail Vikas Nigam
Ltd, entails:
1.
Rail connectivity to four major metro – Delhi, Kolkata, Chennai and
Mumbai – through the Golden Quadrilateral route and its diagonals.
2.
Rail connectivity to major ports through feeder lines connecting the GQ
route
3.
Construction of four mega bridges over major rivers – Bogibeel over
Brahmaputra, two over Ganga (at Patna and Munger) and one over Kosi at Nirmali.
Related Stories:
Rail Vikas Nigam gets Rs.750 crore for NRVY (08-Jul-03)
Foundation stone for Kosi Bridge project to be laid (04-Jun-03)