Illustrative image – not actual.The Union Railway minister Mr. Lalu Prasad Yadav presented the fifth consecutive railway budget. The key highlights of the budget are as follows;
Review of performance & revised estimates of the budget;
-
Revised target for loading 790 million tonnes - expected growth in goods earnings 14%
-
Operating ratio likely to improve from the budgeted 79.6 to 76.3 per cent –best in last four decades
-
Return on capital - an all time high of 21 per cent
Initiatives in Passenger Business
-
Increase in UTS counters to to 15,000 and ATVM s to 6000 over two years
-
Extension of Jansadharan ticket booking seva
Passenger Amenities
-
Provision of discharge-free green toilets in all 36,000 coaches in XI Plan Period at a cost of about Rs.4,000 crore
-
Increase in the height of a number of platforms
-
Provision of platform shelters at all D category stations
-
Provision of foot-over bridges at all high-level platforms
-
Increase in length of 30 more platforms
-
Provision of multi-level parking, lifts and escalators at major stations
Initiatives in Freight Business
-
Target for loading kept at 850 million tonnes in 2008-09 - incremental loading of 60 million tonnes or more, consecutively for the fourth year
-
Blue print prepared for high density network: phased execution of capacity augmentation including dedicated freight corridors, doubling, third and fourth lines, bye passes, flyovers, automatic signaling works etc over next 7 years at cost of about Rs.75,000 crore
-
Enhancement of railway routes for important coal linkages
-
Port connectivity projects to be given high priority to achieve traffic target of mission 300 million tonnes
-
Work on the Eastern freight corridor from Ludhiana to Dankuni (Kolkata) and Western freight corridor from Delhi to JNPT to start in 2008-09
Other major initiatives
-
Public Private Partnership schemes to be launched for attracting investment of Rs.1,00,000 crore over the next five years for developing world class stations, rolling stock manufacturing, multi modal logistics parks, running of container trains etc Commercial use of railway land by Rail Land Development Authority to give boost to Railway Revenues
-
For the staff welfare, 2 divisional hospitals at Jaipur and Hubli to be upgraded to central hospitals and a new divisional hospital at Ranchi, and an OPD block at ICF to be constructed
The Annual Plan for 2008-09
-
The annual plan outlay of Rs.37,500 crore has been chalked out so far support of Rs.7,874 crore from general revenues, internal resources of Rs.21,126 crore and extra budgetary resources of Rs.8,500 crore
-
Thrust areas of annual plan include activities relating to throughput enhancement of high density network routes, improvement and expansion of traffic facility and network, construction of flyovers, bypasses, IBS, upgradation of goods shed
-
Project plans outlay: New lines entailing Rs.1,730 crore, gauge conversion Rs.2,489 crore, electrification Rs.626 crore, Metropolitan transport projects Rs.650 crore
-
Safety related plan outlays: Track renewal Rs.3,600 crore, bridges Rs.600 crore, signal & telecommunication works Rs.1,520 crore, road over/under bridges Rs.700 crore and manning of unmanned level crossings Rs.600 crore
-
A total of Rs.11,045 crore has been chalked out for outlay for rolling stock
-
Outlay for passenger amenities Rs.852 crore
-
Important targets: New lines of 350 kms, gauge conversion 2,150 kms, doubling 1000 kms
-
National projects: Funds to be made available by Ministry of Finance based on the actual progress of works during the course of the year. Rs.1,712 crore asked for from Ministry of Finance
-
The number of National projects increased from 4 to 8
-
MUTP Phase II to be started at a cost of Rs.5000 crore, financed jointly by Railways and State Government of Maharashtra, with multi-lateral funding
-
Indian Rail Bijli Company Ltd.- a joint venture with NTPC for 1,000 MW thermal power plant at Nabinagar district of Aurangabad, Bihar
-
A new rail coach factory to be set up in Kerala
-
A new wagon re-construction unit to be set up at Garkha in Chapra district
-
Modernization and development of Jamalpur Workshop
-
Modernization of Lilluah workshop , Perambur loco workshop, Ajmer loco workshop
-
Railways to takeover Mokama and Muzaffarpur wagon factories