Here are extracts from the Railway Budget Speech, made by Union Railways Minister, Mr Nitish Kumar, on 26 February 2003.

Navigation Guide

(Use the Back button of your browser to return to navigation guide)

 

Introduction

Financial Performance in 2002-03

Special Railway Safety Fund (SRSF) - Financial & Physical progress

Other Initiatives

Projects

New Lines

Guage Conversion

Doubling

Mega Terminals

Suburban Transport Projects

Railway Electrification

Annual Plan; 2003-04

Budget Estimates: 2003-04

Freight Services

 

Introduction

At the outset, I express my profound gratitude to Honourable Prime Minister for launching the National Rail Vikas Yojana, which involves the strengthening of the Golden Quadrilateral, augmenting rail connectivity to ports and also the construction of four mega bridges.

This non-budgetary initiative is bound to accelerate the growth of the Indian Railways, which is the life line of the nation.

Review of Financial Performance in 2002-03

In the Budget for 2002-03, the originating revenue earning freight traffic has been estimated at 510 million tonnes. I am happy to inform the House that the performance during the first 10 months of the current fiscal has exceeded the proportionate target.

Accordingly, the target for the originating revenue earning freight traffic has been revised upwards to 515 million tonnes in the Revised Estimates for the year. On the other hand, in the Passenger segment there has been a drop of nearly three per cent in number of passengers to end December 2002. 

The goods earnings are likely to exceed the Budget target of Rs.26,118 crore by Rs.540 crore, whereas passenger earnings are likely to fall short of the Budget target of Rs.13450 crore by Rs.720 crore.

Taken together, the other coaching and sundry earnings are likely to be Rs.24 crore below the Budget target. Due to continued increase in the amount owed to Railways by the users, particularly, Electricity Boards, the unrealised earnings are likely to increase by Rs.417 crore as against a budgeted clearance of Rs.50 crore. Therefore, the budgeted Gross Traffic Receipts of Rs.41,538 crore have been reduced to Rs.40,867 crore in the revised estimates.

With sustained monitoring and continued austerity, there is likely to be a reduction of Rs.850 crore in the ordinary working expenses. Accordingly, the revised estimates for these are placed at Rs.30,310 crore as against Rs.31,160 crore in the Budget estimates.

The operating ratio budgeted at 94.4 per cent is likely to improve to 92.5 per cent in the revised estimates.

Besides discharging fully the dividend liability for the year, an amount of Rs.50 crore is also proposed to be cleared from the Deferred Dividend Liability Account. 

Continuous Track Circuiting

Continuous track circuiting enables detection of discontinuities caused by rail/weld fracture or acts of sabotage. This helps in taking timely precautionary measures and prevents possible accidents. This will also improve the line capacity and safety at level crossing gates. The work of track circuiting is being executed within station limits. Work of continuous track circuiting in block sections on selected sections of A, B and C routes at a cost of Rs.425 crore is now being proposed in this Budget.

Bridges

For upgrading and modernizing the bridge inspection and management systems, action has been taken to initiate underwater inspections, computerized non-destructive testing with state-of-the-art equipment and introduce a modern Bridge Management System.

Crash worthiness of Coaches

To minimise injuries during rail travel, coaches are being redesigned without any sharp corners in the interior and duly padding up vulnerable areas. In order to prevent coaches from climbing over each other in the event of a collision, tight lock couplers are being introduced progressively.

Concurrently, redesigning coach ends to take the full impact of the collision has been undertaken so that passenger areas remain free from damage due to collision or heavy impact.

Special Railway Safety Fund (SRSF) - Financial & Physical progress

During 2001-2002 the actual expenditure under SRSF stood at Rs.1434 crore (Net) as against the allotment of Rs.1400 crore.

The safety surcharge fell short of the targeted collection by Rs.95 crore. Thus, the additional amount of Rs.129 crore required on both these counts was made available through Railways normal revenues. In the current year, the total net allocation for SRSF was stepped up to Rs.2210 crore as per the Budget Estimates, which included Rs.1350 crore as contribution from the general exchequer and Rs.860 crore from the safety surcharge.

This has been further increased by Rs.100 crore in the revised estimates to keep up the pace of progress of safety works under SRSF. Railways are contributing this additional amount as well as the current years shortfall of about Rs.200 crore in surcharge collection from its own revenues. 

As regards the physical progress of the works, I would like to inform that track Renewal of around 5,400 km is also expected to be completed by the end of the current year.

Rehabilitation of approximately 745 bridges is likely to be completed by the end of the current financial year. So far signalling equipment replacement works have been completed at 298 stations. Further, about 1350 track circuits have been provided till now. 

Other Initiatives

Joint Venture with NTPC

As was reported last year, an  MoU was signed by the ministry of railways with NTPC for setting up of captive thermal power plants. I am happy to state that the project committee consisting of representatives from NTPC and Railways formed for the purpose has, after examining four different sites, recommended Nabinagar as a suitable site for a 1000 MW thermal plant, which has been accepted. It is now proposed to form a Joint Venture Company of Railways with NTPC for implementation of the scheme.

Bio Diesel

The Railways are also exploring alternative fuel sources. A massive drive for planting Ratan Jyot plants on both sides of the Railway land has been embarked upon. Bio-diesel, which can be distilled from Ratan Jyot by a simple and inexpensive refining process, can be freely mixed with diesel oil used on our locomotives. This is an initiative that is not only environment-friendly, but will also result in reducing our fuel bill.

Projects

National Rail Vikas Yojana

National Rail Vikas Yojana, announced on 15th August, 2002, at an estimated cost of Rs.15,000 crore, has been formally launched on 26th December, 2002 by the Honble Prime Minister. A company named "Rail Vikas Nigam Limited" has been incorporated under the Companies Act for implementation of these projects including raising of resources.

Strengthening of the Golden Quadrilateral and its diagonals through identified sub-projects costing about Rs.8,000 crore (Rs.80 billion) will form the major part of this yojana. A part loan of $ 313.6 million has been approved by ADB. It will be utilized, mainly, for execution of projects covered under the initiative of "strengthening of Golden Quadrilateral". A dialogue with World Bank has been initiated to mobilize funds for "mega bridges" and other NRVY projects. Projects under the initiative "port connectivity" have been identified and resource mobilisation for the same is proposed to be organized through various public-private partnership initiatives and budgetary support.

Sir, as committed in my last budget speech, work has already commenced on three mega bridges i.e., Bogibeel bridge over river Brahmaputra, two bridges over river Ganga, one at Patna and the other at Munger. I am happy to inform the House that the requisite clearances for the mega bridge over river Kosi have been obtained and the work has been included in the Budget.

National and strategic projects

Honourable Prime Minister, during his visit to Srinagar had announced that the first train will roll into Kashmir Valley by 15th August 2007. I express my gratitude to the Hon'ble Finance Minister, who has provided Rs.. 500 crore for this National project in 2003-04, considering its importance.

The work on Udhampur-Katra and Quazigund-Baramulla sections is already in progress.

The stretch between Katra-Quazigund is very difficult requiring large scale tunneling and bridging works for which detailed surveys on ground need to be carried out. Considering the arduous nature of work, construction on this section has been entrusted to two technically sound organizations, viz., IRCON and Konkan Railway Corporation Limited while detailed survey has been entrusted to RITES. I am happy to inform that long pending project of Jammu-Udhampur is progressing at a satisfactory pace and is targeted for completion by March 2004. Further, rail link up to Katra is likely to be completed during 2004-2005.

The two strategic projects, namely, gauge Conversion from Luni to Munabao and new line between Kolayat and Phalodi are progressing satisfactorily and gauge Conversion up to Samdari has already been completed.

Over 1300 km of BG lines are likely to be added during the current year. Further, a target of addition of nearly 1340 kms of BG lines has been set for 2003-2004.    

New Lines

Sir, I am happy to state that Kumarghat-Manu of Kumarghat-Agartala new line has already been completed and commissioned on 27.12.2002 for passenger services. The restoration of Fatuha-Islampur has also been completed. It is hoped to complete restoration of Duraundha-Maharajganj and new lines between Katra-Faizabad and Joruli-Keonjhar during the year. Further, the work of Daulatpur-Malikpur and Bajkul-Nachenda are also likely to be completed by March 2003. The balance targeted portion of these lines i.e. from Malikpur to Balurghat and Nachenda to Kanthi are expected to be completed by June 2003.

In 2003-2004, Railways propose to complete 225 km of new lines including following sections:

  • Panvel-Karjat
  • Sasaram-Nokha of Ara-Sasaram
  • Kakdweep-Namkhana of Lakshmikantapur-Namkhana
  • Bajalta-Udhampur of Jammu-Udhampur
  • Una-Churaru Takrala of Nangaldam-Talwara
  • Kakinada-Kotipalli restoration
  • Mahendralalnagar-Amta of Howrah-Amta
  • Hassan-Sharavanabelagola of Hassan-Bangalore
  • Tilaiya-Jagdishpur of Rajgir-Tilaiya

Gauge Conversion

 

During the year, the gauge Conversion of Vadalur-Vriddhachalam, Dharmabad-Nizamabad and Jankampet-Bodhan has already been completed. I am happy to state that against the original target of 791 km of gauge Conversion set for the current year, nearly 900 km of gauge Conversion is likely to be achieved. This includes Latur-Latur Road new line portion of Miraj-Latur, Mangalore-Kabakaputtur, Virudunagar-Rajapalaiyam, Katpadi-Pakala-Tirupati, Surendernagar-Pipavav, Rajkot-Junagarh and Samdari-Jasai where the works of mega block are already in progress.

 

During the year 2003-2004, a target of over 775 km of gauge Conversion has been proposed which include the following sections:

  • New Jalpaiguri / Siliguri-Samuktala of New Jalpaiguri-New Bongaigaon
  • Bandikui-Bharatpur of Bandikui -Agra
  • Jasai-Munabao of Luni-Munabao
  • Kabakaputtur-Subrahmanya Road of Hassan-Mangalore
  • Villupuram-Pondicherry
  • Rajaalaiyam-Tenkasi of Quilon-Tiruchendur and Virudunagar-Tenkasi
  • Vadalur-Cuddalore of Salem-Cuddalore
  • Thanjavur-Kumbakonam of Thanjavur-Villupuram
  • Gondia-Balaghat of Jabalpur-Gondia
  • Junagarh-Veraval with extension to Somnath of Rajkot-Veraval
  • Dhola-Bhavnagar

Further, I am happy to announce that the works of Bhind-Etawah new line as part of Guna-Etawah and Mansi-Saharsa gauge Conversion are in good progress and likely to be completed during the year 2004.

Doubling

 

During the current year about 200 km of doublings are likely to be completed, while in the next financial year a target of 340 km has been proposed.

 

Hon'ble MembeRs.will be happy to know that doublings of Pakni-Mohol, Mansi-Maheshkhunt, Rohtak-Jakhal, Hapur-Kankather, Sahibabad-Anand Vihar 3rd and 4th line, Ambaturai-Kodaikkanal, Chennai Beach-Korukkupet, Kataiya Dandi-Lohgara, Shujalpur-Akodia, Barauni-Tilrath, Barharwa-Tinpahar, Kayankulam-Cheppad and Kayankulam-Mavelikara, Jahanabad-Bela and Chandpara-Bangaon have been included in the budget. Further, doubling of Raichur-Guntakal, Cuttack-Barang, Khurda-Barang 3rd line and Aligarh-Ghaziabad 3rd line have also been included to strengthen Golden Quadrilateral. The completion of these works is expected to ease the traffic flow and create additional capacity on some of the saturated sections.

Mega Terminals

 

While there have been persistent demands for introducing new trains from the Metros, terminal constraints are a major bottleneck. To overcome this, proposals for development of additional terminals at Chitpur, Kolkata and Anand Vihar, Delhi have been included in this Budget.

Suburban Transport Projects

 

I am happy to state that necessary approvals for the Mumbai Urban Transport Project – Phase-I have been obtained. The project envisages upgradation of the rail infrastructure in the city of Mumbai and will go a long way in reducing the overcrowding of commuteRs.in the Mumbai Suburban Rail System. The project involves a loan component of Rs..1613 crore, which has been sanctioned by the World Bank. The work is expected to be completed in 5 years.

 

I am glad to inform the House that the work on the balance portion of 5th line from Andheri to Borivali has been completed. The work of automatic block signalling from Virar to Dahanu Road has also been completed, enhancing the line capacity of the section.

 

EMU services on Barasat-Hasnabad have been commissioned on 22.12.2002. The extension of Kolkata Metro from Tollyganj to Garia is progressing satisfactorily. Extension of Circular Railway from Princepghat to Majerhat and its connection to Netaji Subhash Chandra Bose Airport is likely to be completed by December 2004.

 

I am happy to state that gauge Conversion of Chennai Beach to Egmore has been commissioned recently. The section from Tambaram to Chengalpattu is likely to be completed by March-2004.

 

Hon'ble MembeRs.would be pleased to know that considering the public need, it has been decided to provide a direct link between Chennai Central and Chennai Egmore. This link would benefit commuteRs.as well as long distance passengeRs.and would relieve them of the irksome transhipment between the two stations. As regards MRTS, the work of Tirumailai to Vellachery is expected to be completed by June 2003.

 

The multi-modal transportation system for the twin cities of Hyderabad and Secunderabad, is making satisfactory progress and upgradation of railway infrastructure in Hyderabad-Secunderabad-Falaknuma section and Hyderabad-Lingampalli sections is likely to be completed by March 2003.

 

There have been demands of beautification of the stations on circular railway at Kolkata in order to improve overall ambience along the bank of river Hoogly. I am happy to inform that it is proposed to give face-lift to the stations along with plantation and ornamental fencing in between the stations so as to bring about overall improvement in the surroundings.

Railway Electrification

 

Railway Electrification works have progressed satisfactorily during the year and 208 route kms. have been energized up to January, 2003. It is proposed to electrify a total of 375 route kms. during the current year. By the end of March 2003, 16376 route kms (25.98 percent) on Indian Railways will be electrified.

Annual Plan 2003-2004

 

Sir, I would now like to present the Annual Plan 2003-2004. The Plan outlay for 2003-2004 has been kept at Rs..10,607 crore. Taking into account the outlay of Rs.2,311 crore on safety related works through the Special Railway Safety Fund (SRSF), the total outlay comes to Rs.12,918 crore. This is Rs.603 crore higher than the Revised Estimates of last year. For the year 2003-2004, the total funds received from General Exchequer are Rs.6,577 crore, including Rs.1,600 crore as contribution towards the SRSF and Rs.433 crore from the Central Road Fund. This also includes Rs.730 crore specifically for investment in the newly created Rail Vikas Nigam. The corresponding figure for 2002-2003 was Rs.5,840 crore, including Rs.1,350 crore for the SRSF and Rs.450 crore from the Central Road Fund.

 

In addition to the budgetary support, Railways propose to provide Rs.2,630 crore for plan expenditure through internal resource generation. This is at the same level as was budgeted for last year. The balance requirements of the Plan would be met through extra-budgetary resources, which include Rs.2,970 crore as market borrowing from Indian Railways Finance Corporation and Rs.30 crore as investment through a "BOT" project in the Viramgam-Mehsana Gauge Conversion work. For the Special Railway Safety Fund, the contribution of the Central Government would be supplemented to the extent of Rs.711 crore through Safety Surcharge, taking the total outlay under SRSF to Rs.2,311 crore.

 

Sir, the total outlay under capital on the five major plan project heads this year has been kept at Rs.2,716 crore with Rs.1,005 crore on New Lines, Rs.703 crore on Gauge Conversion, Rs.443 crore for Doubling and Rs.122 crore for Electrification. The outlay on metropolitan transport projects, which has been kept at Rs.443 crore, includes multi-lateral funding for the Mumbai Urban Transport Project.

 

Apart from this, Rs.730 crore are being allotted to several works in the planheads New Lines, Doubling, Gauge Conversion and Railway Electrification, which are to be executed by the Rail Vikas Nigam.

 

The outlay on safety related planheads, inclusive of outlay given under the Special Railway Safety Fund, is Rs.2605 crore (Rs.26.05 bn) for track renewals, Rs.302 crore (Rs.3.02 bn) for the bridges and Rs.689 crore (Rs.6.89 bn) for signalling & telecommunications.

Budget Estimates: 2003-04

 

The Railways are expecting to carry 540 million tonnes of revenue earnings originating traffic during 2003-2004, which is 25 million tonnes more than the traffic of 515 million tonnes likely to be lifted in the current year and this increase is higher than the average incremental freight achieved in the last few years. However, taking note of the prevailing trend in the economy and the various measures being taken by the Railways, this target is expected to be achieved. The originating passenger traffic is estimated to go up by about 3 per cent resulting in increase in earnings of 7 per cent over the Revised Estimates of the current year. The 'Other Coaching' earnings are expected to grow by 7 per cent. Sundry Other Earnings, for 2003-2004 have been estimated at Rs.990 crore, representing a growth rate of 5 per cent over the Revised Estimates of the current year.

 

On the basis of these assumptions, the Gross Traffic Receipts (GTR) are estimated at Rs.43,495 crore. These are Rs.2,628 crore higher than the Revised Estimates of the current financial year.

 

Railways' Ordinary Working Expenses estimated at Rs.32,460 crore are 7 per cent higher than the Revised Estimates of the current year. Appropriation to Pension Fund is placed at Rs.6,385 crore. Based upon the anticipated requirement for plan resources, a provision of Rs.. 2005 crore has been made towards Appropriation to Depreciation Reserve Fund .

 

The total Working Expenses will, thus, amount to Rs.40,850 crore leading to the Net Traffic Receipts of Rs.2,645 crore. Net Miscellaneous Receipts are estimated at Rs.888 crore, which also take into account the amount likely to be collected through levy of surcharge on passenger fares for being appropriated to the Special Railway Safety Fund. Thus, the Net Revenue works out to Rs.3,533 crore.

 

A memorandum on the rate of dividend payable to General Revenues has been submitted to the Railway Convention Committee. Meanwhile, dividend for 2003-2004, has been provided at the same rate as adopted for 2002-2003. On this basis, dividend liability for 2003-2004 works out to Rs.2,930 crore. Along with certain other dues, an amount of Rs.2,978 crore becomes payable to the General Revenues. This liability will be discharged in full.

 

The above projections are expected to yield funds sufficient to meet the requirement of the Plan outlay for the year, from the internal resources.

 

With a view to make the Freight rates and Passenger fares competitive and increase Railways' share in transport sector, it is necessary to continue the process of rationalisation and re-balancing of Tariffs. In order to attract more traffic to rail, I am proposing certain other measures and reforms.

Freight Services

 

Sir, for year 2002-2003 I did not make any across-the-board increase in freight rates. For the year 2003-2004, I do not propose any increase in freight rates for any commodity.

 

While rationalising the freight structure, the total number of classes was reduced from 59 to 32 with Class-90 as the lowest class and Class-300 as the highest class. In freight structure so rationalised, the ratio between the highest and the lowest freight rate was reduced from 8.0 to 3.3. It is proposed to reduce further the band of freight rates through compaction in freight classification by lowering the highest class from Class-300 to Class-250. In the revised classification, the total number of classes will be reduced from 32 to 27 and the ratio between the freight rates for the highest and the lowest class will be further reduced from 3.3 to 2.8.

 

To make the freight rates competitive, it is proposed to reduce the classification of certain commodities where Railways are facing stiff competition due to high freight rates. The classification of Petrol for trainload movement is proposed to be reduced by three stages from Class-280 to Class-250, lowering the freight rates by 10.7 per cent. The classification of certain other commodities is proposed to be reduced by two stages. These commodities include High Speed Diesel Oil (HSD), Furnace Oil, Crude Oil, Naptha, Liquefied Petroleum Gas (LPG), Compressed Gases, Lubricating Oils, Iron & Steel, Pig Iron, Iron Scrap, Cement sheets, Petroleum Coke and Soda ash. Some of the liquid commodities, carried in tank wagons, namely Molasses, Bitumen, Refined vegetable oils (Div. A), and Sulphuric acid are also proposed to be charged two stages lower than their existing classes. The proposed reduction in freight rates due to lowering of classification by two stages will range from 5.3 per cent to 9.5 per cent. The classification of Cement, Clinker, Manganese Ore and Caustic Soda Liquid (in tank wagon) are proposed to be reduced by one stage, which will reduce the freight rates by around 3.7 per cent. Details of the re-classification of these commodities, along with the existing and proposed freight rates for selected distances, are given in the Memorandum Explaining the Budget Proposals for Adjustment in Freight Rates and Fares.

 

In order to increase its share in transportation of Petroleum products, Railways are ready to consider long- term agreements with individual oil companies for further reduction in freight rates on sector-to-sector basis if guaranteed volumes of additional traffic are committed for rail movement.

 

There are many commodities, which have a wagonload class only. It has been decided that any commodity, which has only a wagonload class, will be assigned a trainload class one stage lower than its wagonload class. As a result, the freight will get reduced by around 4.00 per cent to 5.26 per cent if such a commodity is now offered for trainload booking.

 

Freight movement on the Indian Railways is predominantly in the form of block rakes from one originating station to a single destination point. However, with a view to reduce the carrying cost of the customers , block rake movement from one originating station to two destination points close to each other and vice-a-versa is also being permitted. At present, such two-point block rakes enjoy the benefit of lower trainload rates only up to the common point of movement. It has been decided that two-point block rakes will now be granted the benefit of trainload rate for the entire distance of transportation.

 

At present, clubbing up to six consignments is permitted in a broad gauge 8-wheeler wagon. In order to provide rail transportation to a larger number of traders and retailers, it has been decided to allow clubbing up to twelve consignments, on payment of Rs.100 for every additional Railway Receipt.

 

The wages of the railway staff deployed in private sidings are being traditionally charged to the siding owners. In order to give relief to the siding owners, Zonal Railways will undertake a thorough review to reduce the cost of railway staff being charged to the private siding owners in a phased manner.

 

Siding owners generating freight earnings of more than Rs.25 crore (Rs.250 million) per annum from traffic originating from their sidings have been designated as Premier Customers of the railways. An incentive scheme for the Premier Customers to help them increase the rail share of transport is being introduced. Premier Customers would be granted a freight rebate of 2 per cent for every five crore rupees of net additional originating freight earnings over the previous financial year generated to the railways. The rebate under this scheme will be granted in addition to any other freight concession availed by them. However, this incentive scheme will be applicable to net additional originating freight earnings from commodities placed in Class-135 and above.

 

 