Illustrative image – not actual.The Railway Board has sanctioned work at an estimated cost of Rs.86 crore for expanding the installed production capacity at Chittaranjan locomotive works (CLW).
CLW will gear up to produce 220 electric locomotives during 2008-09 and 250 locos in 2009-10. The proposed investment is over and above Rs.40 crore sanctioned for additional machines.
It is learnt that a consultant will be appointed shortly (tender to be finalised soon) to advise CLW regarding detailed design and specifications. Physical work on capacity augmentation is expected to begin by mid of 2008 and set for completion by 2009-10.