Illustrative image – not actual.The Centre has disbursed Rs.750
crore for the National Rail Vikas Yojana to be implemented by Rail Vikas Nigam.
It may be recalled that the Rail Vikas Nigam (RVNL) is a Special Purpose
Vehicle under the Ministry of Railways to implement the Rs.15,000 crore
National Rail Vikas Yojana (NRVY). The NRVY was launched in December 2002
comprising of the Golden Quadrilateral project, rail connectivity with ports
and the construction of 4 mega bridges in the country-two over the Ganga and
one each across the Brahmaputra and the Kosi. Of the two bridges over the river
Ganga, one rail bridge will connect Digha and Sonepur near Patna and the other
will be a rail-cum-road bridge between Munger and Khagaria. The bridge over
river Brahmaputra will be at Bogibeel near Dibrugarh in Assam and will form an
important link between the north and south banks. The bridge over river Kosi
will connect Nirmali and Bhaptiahi.
The Golden Quadrilateral Project,
entails an investment of Rs.8,000 crore for strengthening the rail network
between the four metros. While the cost of constructing the bridges is Rs.
3,650 crore, the port connectivity entails an investment of Rs.3,000 crore.
Under the NRV Yojana, new lines would be laid between the 4 metros wherever
necessary and important stations remodeled to enable faster movement of freight
trains at 100 kms per hour. Interestingly, the
Golden Quadrilateral project though comprises of a mere16 percent of the total
rail network is a crucial project as it carries 65 per cent of the total
freight and 55 per cent of the total passenger traffic.
As far as port connectivity related projects are concerned, the project cost is Rs.3,000 crore, and would comprise developing multi-modal corridors to the hinterland using special double-decker wagons.
While most of the projects under
the NRVY, are scheduled for completion in the
next five to six years, the mega bridges project is targeted for completion
within six to seven years. The entire project under the Golden Quadrilateral
project comprising of strengthening of rail network between the four metros is
scheduled for completion in 2008.
The Rail Vikas Nigam has been
floated with an authorised equity capital of Rs.1,000 crore, which would be
brought in by the Railways through budgetary support. The role of Rail Vikas
Nigam would be to float SPVs wherever possible to attract greater equity
participation from other companies. For instance, in case of projects related
to port connectivity, the respective port authorities could be asked to pick up
equity in the SPV.
Additionally, non-budgetary
funding would be provided by the Asian Development Bank, World Bank and other
domestic financial institutions. The Asian Development Bank has already
sanctioned a loan of US$ 313.6 million for these projects while financial
assistance from the World Bank is to the tune of $ 100 million (Rs. 470
crore). Apart from an equity of
Rs.3,000 crore, Rs.5,000 crore is likely to be raised from the market for
financing the projects. The Asian Development
Bank has also expressed its willingness to provide additional loans during 2006
and 2008 for funding NRVY.