Raichur Power project unit 7, being implemented by Karnataka Power Corporation, is likely to be synchronised by December 2002, 2 months ahead of schedule.

 

The purchase of all electro-mechanical packages have been completed and supply and erection of components is in progress. Meanwhile, the hydraulic testing of the boiler at the unit took place on 9 May 2002, 2 months ahead of schedule.

 

Coal for the project would be sourced from Mahanadi Coalfields’ Talcher mines (in Orissa) to Paradip port by railway; from Paradip port to Ennore port by sea and again by railway to the plant site. Coal would also be supplied from Western Coalfields and Singareni Collieries, while the water requirements of 0.4 TMC per annum would be met from River Krishna. The plant is expected to generate about 4 million units of energy.

 

The first 3 stages, involving a capacity of 2 x 210 MW, has already been set up.