Illustrative image – not actual.Raichur Power project unit 7, being implemented by
Karnataka Power Corporation, is likely to be synchronised by December 2002, 2
months ahead of schedule.
The purchase of all electro-mechanical packages have been
completed and supply and erection of components is in progress. Meanwhile, the
hydraulic testing of the boiler at the unit took place on 9 May 2002, 2 months
ahead of schedule.
Coal for the project would be sourced from Mahanadi
Coalfields’ Talcher mines (in Orissa) to Paradip port by railway; from Paradip
port to Ennore port by sea and again by railway to the plant site. Coal would
also be supplied from Western Coalfields and Singareni Collieries, while the water
requirements of 0.4 TMC per annum would be met from River Krishna. The plant is
expected to generate about 4 million units of energy.
The first 3 stages, involving a capacity of 2 x 210
MW, has already been set up.