Raichur Power project facing cost overrunIllustrative image – not actual.
Raichur Power Corporation is facing cost overrun at 1,600 MW ultra supercritical coal based power unit in Karnataka.

 

The project is facing cost overrun of Rs 2,318 crore, which the company expects to fund by a mix of debt and sponsors contribution.

 

The overrun is mainly due to non-availability of mega power status, escalation in plant costs, and adverse changes in foreign exchange and interest rates during construction.

 

The project is a joint venture between Karnataka Power Corporation Ltd (50 per cent), BHEL (26 per cent) and IFCI Ltd (24 per cent).

 