Raghunathpur power plant starts operationsIllustrative image – not actual.
Unit-I of Damodar Valley Corporation’s Raghunathpur Thermal Power Plant has set out with steady progress from the early morning of Sunday. The 600 MW Unit-I is part of the 1,200 MW Stage-I of Raghunathpur project located in Purulia district of West Bengal.


DVC has already started civil work for the boiler of the 660 MW Unit-I of 1,320 MW Stage-II. The project is likely to be completed in two years.


The thermal power plant is of paramount importance to power-intensive cement and ferro-alloy industries at Raghunathpur and Barjora industrial parks.


Ambani firm and Emami have both invested in 100 acre each for setting up cement plants in Raghunathpur Industrial Park. Their total investment is Rs 600 crore and Rs 500 crore, respectively.

 