Illustrative image – not actual.Reliance Power (R-Power) expects to complete the 2,400 MW gas fired power project at Samalkot in Andhra Pradesh ahead of schedule, as the first batch of two gas turbines reached the project site a month in advance.
The gas turbines from General Electric's facility at Greenville, South Carolina in US reached Kakinada port, from where they were flagged off to the plant site on 16 June 2011.
The Rs 10,000-crore project is scheduled to go into open-cycle commissioning by March 2012, while the combined cycle commissioning has been scheduled for December 2012.