Illustrative image – not actual.Reliance Power (R-Power) has completed the hydrostatic test for its Unit I of 660 MW at the 3,960 MW Sasan ultra mega power plant (UMPP) in Madhya Pradesh.
The test is a milestone in boiler construction and last of the tests conducted to ensure completion, compliance and safety before the boiler produces steam. The Unit I will be commissioned by December 2012. The subsequent units of the 6 x 660 MW UMPP will be commissioned in phases thereafter at three month intervals. The estimated cost of the project is Rs 19,500 crore.
Related Links:
Project profile