PWD to bear cost  for Sangli-Kolhapur four laning projectIllustrative image – not actual.
Maharashtra PWD will now bear the cost of land acquisition for the 11 km long stretch from Jaisinghpur to Sangli, on the Sangli-Kolhapur four laning project.

 

The PWD will make a payment of Rs 30 crore to land owners between the Sangli-Jaisinghpur stretch.

 

With this new development, the project will take a year for completion. The earlier deadline to complete the road construction was October 2014. The total project cost now stands at Rs 270 crore as against the previous Rs 196 crore for the earlier deadline of October 2014.

 

The proposed flyover at Hatkanangale town will now be a reinforced cement concrete construction, where pillars will be erected. It will leave a lot of space under the bridge, which can be used for parking lots. This flyover, which is not even one km long, will cost Rs 24 crore and need one year to construct.

 

The department has cancelled another flyover at Jaisinghpur and decided to widen the bypass to the city. This change will save around Rs 12 crore for the PWD.

 