Illustrative image – not actual.The Punjab government’s proposed Malwa Canal project, involving construction of a 149-km canal, has faced a legal setback after the Punjab and Haryana High Court halted land acquisition proceedings until the Environmental Impact Assessment (EIA) report is finalised.
In its August 25 order, the court directed that petitioners and similarly placed landowners cannot be dispossessed of their land, and no compensation awards can be passed in connection with the project until completion of the EIA. The case involves 273 landowners from Muktsar, Faridkot and Ferozepur districts who challenged the land acquisition process initiated for the canal. The proposed canal is planned to pass through Ferozepur, Faridkot and Sri Muktsar Sahib districts.
Further progress on land acquisition and construction will therefore depend on completion of the environmental assessment and compliance with the Court’s directions.