Pune Metro Project unlikely to see major cost, time overrun amid COVID-19 lockdownIllustrative image – not actual.
The countrywide lockdown has impacted the Pune Metro project forcing the authorities to push back the trial run scheduled for May 2020, but it is unlikely to lead to a significant cost and time overruns.
 
The work has resumed since 1 May 2020 and also the availability of labour is not going to be a major concern for the project.
 
The Rs 11,420 crore  Pune Metro project with two corridors – Line-1 from PMC to Swargate (16.589 km) and Line-2 from Vanaaz to Ramwadi (14.665 km) was scheduled to oprationalise on one line (Corridor-2) in 2020, while the second line (Corridor-21) was schedule for completion by 2021.
 
Two priority sections of five km length on each corridor – PCMC to Range Hill on Line-1 and Vanaz to Civil Court on Line-2 -- were schedule to start trial runs in May 2020.
 
The authorities are uncertain of the trial runs but have started work of the project. The authorities are looking at last quarter operationalisation of the priority sections.
 
Despite the project facing delays owing to parliamentary and assembly elections and the extended monsoon in 2019, it had managed to conduct trial run of coaches within a span of 30 months and was readying to commence technical trial run and go-ahead for regulatory clearances and certification before COVID-19 struck.
 
Due to this, the work was halted for nearly 45 days and the authorities were forced to invoke majeure clause to cushion themselves against the delay.
 
The Maha Metro has sought an extension of the moratorium period from the international lending. The project is being funded via bilateral loan of EUR 600 million from the European Investment Bank and EUR 245 million from AfD. Also, the project vendors and contractors have sought for extension of contract period to complete the project.
 
However, significant cost overrun is not expected due to delay with wages paid to workers being the only significant overheads during the lockdown.
 
In fact, handling of labour will allow Maha Metro and its contractors, namely, Tata Gulemark, URC Construction, NCC, J Kumar, HCC, Shapoorji Pallonji and Afcons, to speed up the work now as the lockdown restrictions have been eased.
 
Of the 8,000 workers on the site in Pune and Nagpur, a majority have stayed back during the lockdown. Around 3,000 of the 4,000 workers in Pune in the pre-lockdown period are available.
 
The authorities now focus on completing the critical works along the river front, as rains are expected to hit soon. Moreover, work is also underway at two railway station coming up on the riverfront.
 
It is expected that work will resume soon at the entire operational area barring Shivaji Nagar.

 