Pune Metro project is likely to operationalise its first two stretches before the end of 2021. The Commissioner of Metro Rail Safety (CMRS) completed the first inspection recently.
This is significant as the project has lost nearly eight months of activity since the onset of the pandemic in 2021, with Pune registering a high number of COVID-19 cases and witnessing the migration of labour on account of lockdowns.
The inspection by CMRS is an important milestone, as it is CMRS that authorises the opening of a Metro corridor, though there will be multiple inspections before final certification is granted.
There was only 40-50 percent of labour on the sites for three-four months due to surge in COVID-19 cases and this affected the pace of work. The end of the second COVID-19 wave has allowed 70-80 percent of labour to return to the sites, ensuring a pick-up in work on the project.
Phase-I of the Pune Metro project entails construction of two corridors – Corridor-1 from the Pimpri-Chinchwad Municipal Corporation (PCMC) to Swargate (17.4 km) and Corridor-2 from Vanaz to Ramvadi (15.7 km), with a total length of 33.2 km.
The two priority stretches MahaMetro is looking to operationalise in 2021 extend from PCMC to Dapodi on Corridor-1 (7.5 km) and from Vanaz to Garware College (5.1 km) on Corridor-2 – technical trial runs on the Vanaz to Garware College stretch commenced from 8 July 2021.
Apart from these two corridors, a third line is to be built in public private partnership (PPP) mode, with the Pune Metropolitan Regional Development Authority having signed an agreement with TRIL Urban Transport, a subsidiary of Tata Realty, and Siemens Project Ventures, a subsidiary of Siemens Financial Services, for 23.3 km line from Hinjewadi to Shivajinagar.
Land acquisition challenges had delayed commencement of work on Rs 8,100 crore project. With the state government approval in May 2021, leasing of 4.75 ha at Balewadi to the Tata-Siemens venture for commercial use, decks have been cleared for work to start on Line 3.
While the government had earlier announced that all the three lines would be operational by 2022, the project is unlikely to meet the timeline due to delays caused by the pandemic and land acquisition issues.
The half of Rs 11,420 crore expenditure on Phase-1 of the project is being borne by the Centre and the state government (20 percent each) and the Pune Municipal Corporation and PCMC (5 percent each).
The remaining amount is being raised through loans from EIB and AgenceFrancaise de Development (AFD). EIB has approved a loan of EUR 600 million (Rs 5,400 crore) for the project while AFD is providing EUR 245 million (Rs 2,000 crore).
With the city having grown significantly since the first phase of the project was conceived, the need is already being felt to extend the approved corridors and build new ones. The detailed project reports (DPRs) are in the works for 123.5 km of lines.
The state government has already approved lines with a total length of 82.5 km.
Work on a 4.4 km extension of Corridor-1, from PCMC to Nigdi, is likely to start first, with the government forwarding its DPR to the Centre in April 2021.
The DPR for an extension of Corridor-1 from Swargate to Katraj is in the process of being approved by the civic body in Pune. Moreover, an extension of Line 3 from Shivajinagar to Hadapsar has also been mooted.