Illustrative image – not actual.Power Trading Corporation (PTC) and Power Grid Corporation of India (PGICL) have entered into an agreement for setting up the Indian portion of the 132 kV Anandnagar (India) - Butwal (Nepal) transmission line.
According to the agreement, PGCIL would set up the transmission line at a cost of Rs.18.5 crore with (LILO) loop in loop out of one circuit at Maharajgunj substation in Uttar Pradesh along with associated bays. PTC would pay future charges for the transmission line that would be constructed, operated and maintained by PGCIL.
The agreement would remain operative till March 2007, with a provision for extension.
Presently, power is exchanged between India and Nepal. However, this exchange of power is in small quantities at 11 kV and 33 kV levels. Bulk transfer of power has not been possible so far.
In order to overcome this problem, there are plans to set up three 132 kV transmission lines between India and Nepal over the next 2 years. The Anandnagar-Butwal line is one of these, which would connect Nepal with power starved northern India.
It may be mentioned that Nepal would reportedly, have excess power of about 100-150 MW from May to October for the next 15 years, which could be used by India.